The road to owning a house. Final weeks.

Week 25&26. 18th - 31st December 2017 The house is finally practically completed. The consultants pushed the contractor to work through Christmas to handover the house on 29th December. The interior designer also folded her sleeves to make the handover complete. The interior designer making some patterns on one of the feature walls. The landscape designer was not left behind... he too put in the...

The road to owning a house. Week 24 – Finishes part 11

Week 24 .  11th -16th December 2017 The new completion date has been moved from 15th - to a date that is now not known to the client. The client now says he’s not sure anymore about the actual completion date….but hopes it will be practically complete before the end of the year. Paint work ongoing as per Interior Designers specifications Paint work ongoing as per Interior Designers...

The road to owning a house. Week 23 – Finishes part 10

Week 23 .  4th -9th December 2017 The new completion date has been moved from 15th -around 20th December 2017. The client now says he's not sure anymore about the actual completion date.... External paint. Cake of the week. To order call 0724771009 Internal doors Tiles done The client will continue working on  the finishes this week under the guidance of the Interior designer Ms. Wamuyu. We...

The road to owning a house. Week 22 – Finishes part 9

Week 22 . 27th November – 2nd December 2017 End of initial contract period but the contractor has been allowed an extension. New date of completion is on Dec 15 2017. Manholes leading to the septic tank. They need to slope to allow for the waste to flow using gravity. Kitchen cabinets after the design by the Interior designer. Currently being installed. Cake of the week. All edible. Call 0724 77...

The road to owning a house. Week 21 – Finishes part 8

Week 21 .  20th November – 25th November 2017 End of initial contract  period but the contractor has been allowed an extension. New date of completion is 4 weeks away on Dec 18 2017. Kitchen cabinets after the design by the Interior designer. The tiles await fixing as per the flooring layout provided by the interior designer.  Cake of the week. To order, call 0724771009 Red soil and hardcore...

The road to owning a house. Week 20 – Finishes part 7

Week 20 .  13th November – 18th November 2017 End of initial contract  period but the contractor has been allowed an extension. New date of completion is 5 weeks away on Dec 18 2017. For those who thought that the client doesn't have neighbors. Gypsum work ongoing Cake of the week. To order, CALL 0724771009 External doors now in place The client will continue working on  the finishes this...

The road to owning a house. Week 19 – Finishes part 6

Week 19 .  06th November – 11th November 2017 1 week to initial end of contract period but the contractor has requested for an extension. New date of completion is 6 weeks away on Dec 18 2017. External doors and grills have been fitted. The walls have been skimmed ready for painting Cake of the week. To order call 0724 771009 Windows and grills in place External plaster almost complete The...

The road to owning a house. Week 18 – Finishes part 5

Week 18 .  October 30th  - 04th November 2017 2 weeks to initial end of contract period but the contractor has requested for an extension. New date of completion is 7 weeks away on Dec 18 2017. Septic pit cast with concrete External doors and more plaster. Waiting for the plaster to dry before painting.  Cake of the week . To order call / whatsapp 0724 771009   Underground water tank...

The road to owning a house. Week 17 – Finishes part 4

Week 17 .  October 23 -28th  2017 3 weeks to completion, God willing Electrical wiring ongoing Kitchen beginning to take shape   Few slots remaining for wedding cakes Call Taji Cakes on 0724 771009 Fencing ongoing The client will continue working on  the finishes this week under the guidance of the Interior designer Ms. Wamuyu . The  client has also started engaging a landscape...

The road to owning a house. Week 16 – Finishes part 3

Week 16 .  October 16th -21st  2017 4 weeks to completion, God willing External plastering ongoing Few slots remaining for wedding cakes The client mentioned that he’s getting election period crazy deals for solar water heating and lighting with long warranties. To get the deals call +254 723 477 035. This week the client will continue working on the finishes with the help of the...