Real Estate Valuation, Sales and Research in Kenya

The road to owning a house. Week 22 – Finishes part 9

Week 22 . 27th November – 2nd December 2017 End of initial contract period but the contractor has been allowed an extension. New date of completion is on Dec 15 2017. Manholes leading to the septic tank. They need to slope to allow for the waste to flow using gravity. Kitchen cabinets after the design by the Interior designer. Currently being installed. Cake of the week. All edible. Call 0724 77...

The road to owning a house. Week 21 – Finishes part 8

Week 21 .  20th November – 25th November 2017 End of initial contract  period but the contractor has been allowed an extension. New date of completion is 4 weeks away on Dec 18 2017. Kitchen cabinets after the design by the Interior designer. The tiles await fixing as per the flooring layout provided by the interior designer.  Cake of the week. To order, call 0724771009 Red soil and hardcore...

The road to owning a house. Week 20 – Finishes part 7

Week 20 .  13th November – 18th November 2017 End of initial contract  period but the contractor has been allowed an extension. New date of completion is 5 weeks away on Dec 18 2017. For those who thought that the client doesn't have neighbors. Gypsum work ongoing Cake of the week. To order, CALL 0724771009 External doors now in place The client will continue working on  the finishes this...

The road to owning a house. Week 19 – Finishes part 6

Week 19 .  06th November – 11th November 2017 1 week to initial end of contract period but the contractor has requested for an extension. New date of completion is 6 weeks away on Dec 18 2017. External doors and grills have been fitted. The walls have been skimmed ready for painting Cake of the week. To order call 0724 771009 Windows and grills in place External plaster almost complete The...

The road to owning a house. Week 18 – Finishes part 5

Week 18 .  October 30th  - 04th November 2017 2 weeks to initial end of contract period but the contractor has requested for an extension. New date of completion is 7 weeks away on Dec 18 2017. Septic pit cast with concrete External doors and more plaster. Waiting for the plaster to dry before painting.  Cake of the week . To order call / whatsapp 0724 771009   Underground water tank...

The road to owning a house. Week 17 – Finishes part 4

Week 17 .  October 23 -28th  2017 3 weeks to completion, God willing Electrical wiring ongoing Kitchen beginning to take shape   Few slots remaining for wedding cakes Call Taji Cakes on 0724 771009 Fencing ongoing The client will continue working on  the finishes this week under the guidance of the Interior designer Ms. Wamuyu . The  client has also started engaging a landscape...

The road to owning a house. Week 16 – Finishes part 3

Week 16 .  October 16th -21st  2017 4 weeks to completion, God willing External plastering ongoing Few slots remaining for wedding cakes The client mentioned that he’s getting election period crazy deals for solar water heating and lighting with long warranties. To get the deals call +254 723 477 035. This week the client will continue working on the finishes with the help of the...

The road to owning a house. Week 15 – Finishes part 2

Week 15 .  October 9th -14th  2017 5 weeks to completion The walls are ready for wall tiles and the plumbing works are complete Fabrication of external doors is underway Few slots remaining for wedding cakes   The terrace slab has been cast The floor is now ready for tiles   Preparing to "finish" the septic tank The client mentioned that he's getting election period crazy deals...

The road to owning a house. Week 14 – Finishes part 1

Week 14 .  October 2nd -7th  2017 6 weeks to completion Windows Water tanks Plastering                                      Plumbing works for both cold and hot water. The client mentioned that he's getting crazy deals for solar water heating and lighting with long                                                        warranties. I can share...

Compare listings

Compare